News

HorizonQuarter – A Lighthouse Project in the Making!
An eventful year 2025 is drawing to a close. BlackHorizon would like to sincerely thank all partners for the successful collaboration. At the same time, we are already looking ahead to 2026 with great anticipation, as the next major milestones are on the horizon.

Logistics Hall North – Balmung Medical Visits the Site
In recent weeks, continuous progress has been made on the construction site: the structural shell has been completed, and a large portion of the façade and roofing works are finished. The new logistics center for the future tenant Balmung Medical is clearly taking shape.

Logistics Hall North – Construction Progress on Schedule
Construction of the new Logistics Hall North is progressing rapidly: the steel structure of the high-bay warehouse has been completed, and the precast concrete works on the head building (receiving & order picking) are also nearing completion.

Safety First: The HorizonQuarter Sprinkler Control Center
While the steel construction is already making visible progress, a key element of the safety infrastructure for the entire quarter is being developed beneath the “Logistics Center North” building component: the sprinkler control center, including the control unit, as well as two massive firewater storage tanks, each with a capacity

HQ Logistics Center North: Steel Meets Concrete
Construction activities at the Logistics North building component have been underway since early July. While work in recent weeks focused primarily on below-ground and ground-level operations—among other things on the sprinkler control center in the basement as well as on the strip foundations—the next construction phase is now beginning.

Groundbreaking Ceremony Marks Official Start of Construction for the “HorizonQuarter” in Kirchbichl
On July 10, 2025, the ceremonial groundbreaking marked the official start of construction for the “HorizonQuarter” project in Kirchbichl. On the former site of the Perlmooser cement works, the new headquarters and central warehouse of the globally expanding Balmung Medical Group will be developed, along with modern, high-end office spaces

From Vision to Reality: Construction Begins on the HorizonQuarter in Kirchbichl
The BlackHorizon Group has officially set the starting signal for one of Western Austria’s most exciting construction projects: the HorizonQuarter Kirchbichl Watch the image film now: THE HORIZONQUARTER – IMAGETRAILER On the former site of the Perlmooser cement works, the new headquarters and central warehouse of the Balmung Medical Group

HorizonQuarter – Construction Project Receives Green Light
All required, legally binding approvals for the HorizonQuarter project have now been obtained. These include permits in the areas of construction, trade and commercial law, water and groundwater management, as well as nature conservation. The comprehensive review process carried out by the responsible authorities has been successfully completed—marking a major

Activity at the Construction Site: Site Clearance & Preliminary Work Underway
Another important step toward realization: With the site clearance, the preparatory measures for the Horizon Quarter have officially begun. This brings the actual start of construction within tangible reach. As part of the site clearance, all necessary work to prepare the area is currently being carried out. This includes, among

Sustainability in Focus: HQ Receives DGNB Pre-Certification in Gold
In the era of climate change and ever-growing environmental challenges, emphasizing the sustainability of construction projects has become a crucial guiding principle. An outstanding example of this sustainable approach is HorizonQuarter, which was recently awarded the prestigious DGNB Pre-Certification in Gold. The German Sustainable Building Council (DGNB) thereby honors the

Balmung Medical Moves Headquarters and Central Warehouse to the HQ
We are pleased to announce that Balmung Medical Handel GmbH (www.balmung-medical.com) will be leasing large areas in the HorizonQuarter to accommodate the company’s dynamic expansion and the growing need for additional space. The HorizonQuarter perfectly meets the requirements of this growth phase and provides ideal conditions for the company’s future

Review: Demolition of the Former Perlmooser Cement Plant
With the completion of the technically highly demanding demolition project at the Perlmooserstraße cement plant, an important milestone toward the realization of the new development was achieved in October 2022. Until construction of the new development begins, the partially operational transformer building located on the northern section of the site

HorizonQuarter – A Lighthouse Project in the Making!
An eventful year 2025 is drawing to a close. BlackHorizon would like to sincerely thank all partners for the successful collaboration. At the same time, we are already looking ahead to 2026 with great anticipation, as the next major milestones are on the horizon.

Logistics Hall North – Balmung Medical Visits the Site
In recent weeks, continuous progress has been made on the construction site: the structural shell has been completed, and a large portion of the façade and roofing works are finished. The new logistics center for the future tenant Balmung Medical is clearly taking shape.

Logistics Hall North – Construction Progress on Schedule
Construction of the new Logistics Hall North is progressing rapidly: the steel structure of the high-bay warehouse has been completed, and the precast concrete works on the head building (receiving & order picking) are also nearing completion.

Safety First: The HorizonQuarter Sprinkler Control Center
While the steel construction is already making visible progress, a key element of the safety infrastructure for the entire quarter is being developed beneath the “Logistics Center North” building component: the sprinkler control center, including the control unit, as well as two massive firewater storage tanks, each with a capacity of 500 m³. In an emergency, these systems protect the building complex from fire damage—powerful, redundant, and reliable.

HQ Logistics Center North: Steel Meets Concrete
Construction activities at the Logistics North building component have been underway since early July. While work in recent weeks focused primarily on below-ground and ground-level operations—among other things on the sprinkler control center in the basement as well as on the strip foundations—the next construction phase is now beginning.

Groundbreaking Ceremony Marks Official Start of Construction for the “HorizonQuarter” in Kirchbichl
On July 10, 2025, the ceremonial groundbreaking marked the official start of construction for the “HorizonQuarter” project in Kirchbichl. On the former site of the

From Vision to Reality: Construction Begins on the HorizonQuarter in Kirchbichl
The BlackHorizon Group has officially set the starting signal for one of Western Austria’s most exciting construction projects: the HorizonQuarter Kirchbichl Watch the image film

HorizonQuarter – Construction Project Receives Green Light
All required, legally binding approvals for the HorizonQuarter project have now been obtained. These include permits in the areas of construction, trade and commercial law,

Activity at the Construction Site: Site Clearance & Preliminary Work Underway
Another important step toward realization: With the site clearance, the preparatory measures for the Horizon Quarter have officially begun. This brings the actual start of

Sustainability in Focus: HQ Receives DGNB Pre-Certification in Gold
In the era of climate change and ever-growing environmental challenges, emphasizing the sustainability of construction projects has become a crucial guiding principle. An outstanding example

Balmung Medical Moves Headquarters and Central Warehouse to the HQ
We are pleased to announce that Balmung Medical Handel GmbH (www.balmung-medical.com) will be leasing large areas in the HorizonQuarter to accommodate the company’s dynamic expansion

Review: Demolition of the Former Perlmooser Cement Plant
With the completion of the technically highly demanding demolition project at the Perlmooserstraße cement plant, an important milestone toward the realization of the new development